Update progress: corrected implementation plan

This commit is contained in:
DanConwayDev
2026-01-14 16:04:57 +00:00
parent 8b303d7321
commit e93d600a2e
@@ -395,24 +395,42 @@ The current phased roadmap above is **SUPERSEDED** pending proper planning:
### 2026-01-14 [Session ~18:00]
- Completed implementation plan in strategy document
- Broke work into 6 phases (Phase 0-6) with clear dependencies
- Identified extensive parallelization opportunities:
- Broke work into 7 phases (Phase 0-7) with clear dependencies
- Identified within-phase parallelization opportunities:
- Phase 0: 2 parallel research tracks (NIP-86, nostr-relay-builder)
- Phase 1: 2 parallel tracks (stats cache, storage metrics)
- Phase 2: 2 parallel tracks (NIP-11 extension, user storage events)
- Phase 3: 2 parallel tracks (Prometheus auth, NIP-86 API)
- Phase 4: 2 parallel tracks (SPA, API key management)
- Phase 6: 2 parallel tracks (rate limiting, abuse detection)
- Phase 3: Single track (Prometheus auth)
- Phase 4: Single track (NIP-86 API)
- Phase 5: Single track (dashboard, limited internal parallelization)
- Phase 6: Sequential tasks (quota enforcement)
- Phase 7: 2 parallel tracks (rate limiting, abuse detection)
- Mapped all existing issues to phases:
- 76fe: Phase 1 (verification)
- 7d0b: Phase 2 + Phase 4 (9-12 days)
- 2cdc: Phase 0 + Phase 3 + Phase 4 (7-9 days)
- 8430: Phase 3 + Phase 5 (7-9 days)
- d6ee: Phase 6 Track A (2-3 days)
- 1f4f: Phase 6 Track B (2-3 days)
- 76fe: Phase 1 Track B (verification)
- 7d0b: Phase 2 Track A + Phase 5 (9-12 days)
- 2cdc: Phase 0 Track A + Phase 4 + Phase 5 (8-10 days)
- 8430: Phase 4 + Phase 6 (9-11 days)
- d6ee: Phase 7 Track A (2-3 days)
- 1f4f: Phase 7 Track B (2-3 days)
- Effort estimates:
- Sequential: 29-37 days (6-7 weeks)
- Full parallelization: 20-25 days (4-5 weeks)
- Sequential: 31-39 days (6-8 weeks)
- With within-phase parallelization: 25-30 days (5-6 weeks)
- Added risk mitigation strategies for research and technical risks
- Defined success criteria for each phase and overall
- Each phase must commit working code with passing tests
- Code/commits must not reference phase numbers
- Ready for implementation to begin with Phase 0 research
### 2026-01-14 [Session ~18:30]
- Corrected implementation plan based on feedback
- Fixed incorrect parallelization claims:
- Phase 3 and 4 cannot run in parallel (Phase 4 depends on Phase 0 Track A research)
- Split original Phase 3 into two sequential phases (Prometheus auth, then NIP-86 API)
- Clarified "within-phase" vs "cross-phase" parallelization
- Added explicit deliverable requirements:
- Each phase must commit changes with all tests passing
- No phase references in code comments or commit messages
- Phase 0 commits research docs, all other phases commit working code
- Updated phase count from 6 to 7 phases
- Corrected dependency graph to show true sequential requirements
- More realistic effort estimates accounting for sequential dependencies