Update progress: implementation plan complete

This commit is contained in:
DanConwayDev
2026-01-14 15:51:03 +00:00
parent 94bee02484
commit 8b303d7321
@@ -392,3 +392,27 @@ The current phased roadmap above is **SUPERSEDED** pending proper planning:
- Audit logging: standard INFO messages in app logs
- User storage info: verify nostr-relay-builder support, NIP-44 fallback
- Next: Write implementation plan
### 2026-01-14 [Session ~18:00]
- Completed implementation plan in strategy document
- Broke work into 6 phases (Phase 0-6) with clear dependencies
- Identified extensive parallelization opportunities:
- Phase 0: 2 parallel research tracks (NIP-86, nostr-relay-builder)
- Phase 1: 2 parallel tracks (stats cache, storage metrics)
- Phase 2: 2 parallel tracks (NIP-11 extension, user storage events)
- Phase 3: 2 parallel tracks (Prometheus auth, NIP-86 API)
- Phase 4: 2 parallel tracks (SPA, API key management)
- Phase 6: 2 parallel tracks (rate limiting, abuse detection)
- Mapped all existing issues to phases:
- 76fe: Phase 1 (verification)
- 7d0b: Phase 2 + Phase 4 (9-12 days)
- 2cdc: Phase 0 + Phase 3 + Phase 4 (7-9 days)
- 8430: Phase 3 + Phase 5 (7-9 days)
- d6ee: Phase 6 Track A (2-3 days)
- 1f4f: Phase 6 Track B (2-3 days)
- Effort estimates:
- Sequential: 29-37 days (6-7 weeks)
- Full parallelization: 20-25 days (4-5 weeks)
- Added risk mitigation strategies for research and technical risks
- Defined success criteria for each phase and overall
- Ready for implementation to begin with Phase 0 research