issue: complete phase 0 track a (nip-86 research)

This commit is contained in:
DanConwayDev
2026-01-15 09:55:01 +00:00
parent e70b68e050
commit 5318b58202
@@ -434,3 +434,15 @@ The current phased roadmap above is **SUPERSEDED** pending proper planning:
- Updated phase count from 6 to 7 phases
- Corrected dependency graph to show true sequential requirements
- More realistic effort estimates accounting for sequential dependencies
### 2026-01-15 [Session 09:54]
- Completed Phase 0 Track A: NIP-86 implementation research
- Used subagent to research nostr-sdk 0.43 support for NIP-86
- Key findings:
- ✅ NIP-98 HTTP auth fully supported in nostr-sdk (can leverage for authentication)
- ❌ NIP-86 JSON-RPC protocol NOT provided (must implement from scratch)
- Recommended approach: Implement NIP-86 using existing NIP-98 auth
- Estimated effort: 6-11 days for complete implementation
- Deliverable: `docs/research/nip-86-implementation-options.md` committed
- Next: Phase 0 Track B (nostr-relay-builder user storage events) - deferred for now
- Ready to proceed with Phase 1 implementation